Pouring of Level 2

The pouring of Level 2 at ParqueVista took place on Thursday 30th June. 

Approximately 332 cubic metres of concrete was poured during the course of the day by 45 concrete trucks with block work for Level 2 commencing the following day.

Over 50 workmen were on site including 20 concreters, 5 supervisors and the balance of workers being steel fixers, form workers for block works and post tensioners, all ensuring a perfect pour.